ISONOVA is making excellent headway on their RTO installation.  The duct work and the concrete pad are complete, and the gas service and electrical conduit work are in place.  The RTO machinery was delayed a couple of weeks due to components affected by Hurricane Harvey’s impact on Houston.  The machinery should arrive within the next few weeks.  The project is still on schedule to be up and running before January 1.

At the City’s request, ISONOVA will be shutting down operations at 8 am on Saturday, until 2:30 pm for the Friendship Festival. We appreciate their efforts to ensure that the festival will be pleasant for all our visitors.